Before the actual build begins, there are several important steps that people often overlook and don't factor in.
These are costing, choosing contractors and planning the build, which take 2 to 5 weeks.
Once the preparation is complete, the actual build begins, which takes 4 to 6 months. -
As far as you want. We can prepare just the interior design, or take on the whole process: budget and quotes through our delivery department, renovation, custom furniture and project management through to handover. In the second case you have a single point of contact, and coordinating the contractors is our job.
-
The design process includes four stages:
1. Space planning (2D)
2. Concept design (3D visualizations)
3. Detailed design with a complete, detailed set of drawings for the design and the furniture
4. Budget and quotes for the build (in the Standard + package)
You can learn more about the stages here. Beyond the design, we can also take on project management and the entire delivery of the interior - renovation and custom furniture. -
Project management is a service in which we take on (partly or fully) the monitoring of the correct execution of all processes during the build. It is charged separately because it is not part of the interior design itself, but requires additional dedicated attention and regular involvement from a large part of our team.
-
Setting a budget is an extremely important step in preparing a realistic design that takes your means into account from the start. This way we will create an interior that suits your taste and fits your financial parameters.
-
Choose an interior design studio that best matches your ideas of style, color preferences, functionality, presentation and design stages. Another important factor is whether the studio can also take on the delivery - the renovation works and the custom furniture. This will minimize mistakes during the build.
-
The biggest advantage of working with an established interior design company is that you get your own complete concept in the form of an interior design tailored to your requirements. With an approved design, you can plan the time and cost of building your home properly and save time, effort and money. Another advantage is experience: we tell you in time which decision will cause a problem during the build or make the renovation more expensive, so you do not learn it from the builder.
-
To be as accurate as possible with you, we set a deadline for each design stage separately as early as when we send you our quote. This gives you a clear idea of how long each stage will take, based on our current workload and the size and complexity of the property. Please note that designing an interior is a two-way process and the timeline depends to a large extent on you, as we cannot predict how much time you will need to consider and approve the proposals.
Based on our experience, designing a three-room apartment takes 2-3 months.
Our advice is to contact us as early as possible, without waiting for the building's completion Acts (14, 15 or 16). That way the design is ready when the building is commissioned, and the renovation can start right away. -
Yes. The minimum design area is 55 m². For a smaller area the price is fixed at €2,700 excl. VAT.
-
We recommend working with one company for the entire project, which takes responsibility for both the design and the subsequent delivery of the ideas.
-
Yes. At Fine Design we only design and specify elements that can be 100% built.
-
Yes. Besides homes, we design and deliver offices, clinics, hotels, restaurants, showrooms and all kinds of retail spaces. Our projects include a hotel in the Old Town of Plovdiv, the retro museum at Spa Hotel Markovo, the V-max showroom, the central branch of ING Bank, the Doctor Vandev aesthetic dental clinic, the Tropicana restaurant in Kardzhali and Bamboo Urban.
-
The earlier, the better. If your home is still under construction, do not wait for the building's completion Acts (14, 15 or 16). The design takes 2-3 months, and the preparation before the renovation takes a few more weeks. If you start in time, the renovation begins right after the building is commissioned.
-
Yes. With our new way of working, delivery can run in parallel with the design, so you do not lose time waiting. We agree the details and the price individually, depending on the site.
The build
-
The time needed to complete each renovation task to a high standard in a 110 m² apartment depends mainly on the complexity of the works and ranges from 25 to 55 working days.
-
Before we start the renovation, we send every client a detailed list of the materials they need to choose and buy (quantities of tiles, number of light fittings, etc., by week of the renovation). The client receives and fills in this list online, so we can see how far they have got with ordering materials without unnecessary phone calls and emails. For example, by the second week of the renovation you will need to: choose and buy all the tiles and porcelain tiles specified in the drawings; choose a specific model of parquet or laminate so we can take its thickness and laying requirements into account; and provide us with one sample of each recessed light fitting so we can plan its installation, and so on.
-
This is a common question, and our solution is to cover all these areas with 1.5 cm rubber mats, which keep the covered floors in perfect condition.
-
No. We always work with construction supervision by a member of our team, who organizes the daily work and makes sure everything is carried out correctly and to a high standard. This way you can be sure the exact brief is being delivered with high quality.
-
We work with proven craftsmen who are specialists in their field, and we are the ones responsible to you for the result. That is exactly why we can control the volume of work we take on, never mislead clients about completion times, and achieve the high quality they expect.
-
In the quote we give our clients before signing the contract and starting the renovation, we describe in detail every task that will be carried out, specifying which ones include materials as well as labor. When the renovation works are completed, the site manager walks the client through all completed works and ticks them off on a checklist. This way the client can be sure they have paid for work that has actually been done.
-
The payment schedule is as follows:
- 60% advance on signing the contract.
- 30% interim payment before the installation of light fittings, switches and sockets.
- 10% on handover of the site, with a signed handover certificate. -
The quantities of materials in the renovation quote are taken from the detailed working drawings produced at the end of the design process, and they are calculated precisely when the quote is prepared. This way our clients receive a final price quote before the renovation even starts, and it will not change later.
-
The FineBuilders renovation unit is set up to serve Fine Design clients. The craftsmen we work with know and can read our design studio's drawings without any difficulty, which is definitely one of the reasons renovations run smoothly and without changes to the brief. Even so, we would suggest arranging a meeting where we can review the brief and the working drawings, after which we can tell you whether we can take on the build.
-
Yes, that is possible, but we recommend hiring a single crew for the renovation, which takes responsibility for high-quality work completed on time.
-
Once the renovation quote is ready, we arrange a meeting at our office where we explain and discuss every part of the renovation in detail. After the meeting, we ask our clients to decide within 7-10 days whether they would like us to carry out the renovation works.
For us, planning a renovation is a two-way process in which we don't leave the initiative to our clients. We proceed as follows:
- Once the design is complete, we prepare a detailed quote for all renovation works
- We arrange a meeting at our office where we explain and discuss in detail both the renovation quote and the other quotes for the complete build of the interior
- We schedule the start of the renovation works -
Yes. In recent years more and more leading Italian and Spanish manufacturers have been promoting this size, so we bought a water-jet cutting machine for non-standard tiles and porcelain tiles. We have since started cutting smaller tiles on this machine as well, because the quality of the cut is much higher than with an ordinary tile cutter.